York at Garrison Campus

Project Status
Project Type

The York is a significant residential project designed to expand housing options in Chilliwack. The project consists of multiple buildings, each constructed with a modern architectural style that emphasizes both functionality and aesthetics.

Buildings A and B are already completed and fully operational, providing residents with contemporary living spaces designed for comfort and convenience. These buildings showcase clean lines, large windows, and a thoughtful layout that enhances the living experience.

Building C is currently under construction, continuing the project's commitment to delivering high-quality residential units. This building will complement the existing structures while introducing new features and amenities to serve the growing community.

Buildings D, E, and F have recently been approved, with construction expected to start soon. These future phases will further enhance the residential landscape of Campus Drive, adding more housing options and continuing the cohesive architectural theme established by the earlier buildings.

Gallery

Connected to this Project

Related Buildings

York Building E

Building E at 45495 Campus Drive will provide 95 residential units with a height of 20.4 meters, exceeding original limits for enhanced design. A zoning amendment allows 50% of required storage lockers to be integrated within the units for convenience.
Storeys
6
Units
95
Look at Project

York Building F

Building F at 45495 Campus Drive offers 99 units with a focus on diverse housing options, supported by updated zoning for increased density.
Storeys
6
Units
84
Look at Project

York Building D

Building D at 45495 Campus Drive will feature 74 residential units, with enhanced accessibility and design under the updated CD-24 zoning.
Storeys
6
Units
114
Look at Project
Know something we don't? Let us know if we've made a mistake.

Project Updates

Site prep for Buildings D, E and F at 45495 Campus Drive
August 27, 2024
Photo Update

Construction Progress of Buildings D, E, and F at 45495 Campus Drive

The lot at 45495 Campus Drive shows ongoing development, with construction equipment and materials on-site. Foundations and structures are actively being worked on, although that could just be connected to buildings A, B and C.
View Photos